19 Nov 2017

 

QUINTIN QS ( Kevin Barry) appointed to cost manage the construction of the proposed new Health & Wellbeing Centre as an extension to their existing facilities.

 

 

Update : 19/11/2017

A few photos from earlier today, with blockwork progressing above level of surrounding hoarding.

 

Update: 12/11/2017

Photo taken earlier today showing further progress on the superstructure blockwork.

 

 

Drone shot of works also

 

Update: 5/11/2017

Coulter Construction undertaking works with official start made on 30th September 2017. Anticipated completion April/May 2018. Contract between Ballygalget GAC and Coulter Construction signed off and Valuation 1 certified today.

  1. Power NI on site, trenching complete and moving electricity pole works complete!
  2. Substructures complete as per photo below (30/10/2017)

3. Superstructure blockwork underway as noted below (5/11/2017)

 

Detailed M&E proposals and marking out to be discussed and agreed with Client once walls erected.

Hoped that first floor level be reached during November 2017.