13 May 2025

Update as of May 2025

Construction Progress and Milestones

An artist’s impression of the planned Narrow Water Bridge, showing the cable-stayed span (left) and the opening bascule span (right) across the Newry River at Carlingford Lough.
Construction of the Narrow Water Bridge officially commenced in mid-2024 after decades of anticipation. Site works began in May 2024, with crews clearing ground and mobilizing equipment on both the Omeath (Co. Louth) and Narrow Water (Co. Down) sides of the Newry River. A formal groundbreaking event on 4 June 2024 marked the project’s start, attended by Irish and Northern Irish officials from both jurisdictions. By late 2024, foundation works were well underway: piling rigs operated on both bridge piers throughout November 2024. On the Louth side, a cofferdam and pile cap construction for the southern pylon began to take shape, along with the first sections of a control/maintenance building to house the bridge’s operating equipment (generator, control room, etc.). By January 2025, a large temporary piling platform had been established in the river just off the Omeath shore to facilitate in-water foundation drilling. This allowed contractors to install steel piles for the bridge’s bascule pier and abutments in Carlingford Lough. Drone imagery from early 2025 captured the progress – multiple steel piles protruding from the water and heavy cranes at work on land – evidence that substructures for both the fixed span and opening span are well in progress. The project has thus moved from site preparation into substantive construction: foundations are being completed and preparations for the bridge’s distinctive cable-stayed pylons and rolling bascule mechanism are underway.

Timeline and Schedule

No major schedule slippages have been reported as of May 2025 – officials maintain that the Narrow Water Bridge is “progressing on schedule”. The target timeline foresees roughly three years of construction, putting substantial completion in late 2027, followed by testing and commissioning. Project leaders expect the bridge to be handed over and open to traffic in 2028. This anticipated opening year (2028) aligns with the original plan and was reiterated by the First Minister-designate of Northern Ireland in late 2024. Key milestones achieved so far (site clearance, foundation piling) have occurred on time. Upcoming milestones include the erection of the bridge’s south pylon and twin north pylons in 2025-2026, installation of the cable stays, and assembly of the steel orthotropic bridge deck (including the bascule lifting span). The contractor, BAM Ireland, capitalized on favorable weather in summer 2024 to get an early start, which officials believe will help ensure the timeline is met. No significant delays have been announced up to early 2025; on the contrary, stakeholders regularly express confidence that the bridge can be delivered within the planned schedule. Barring unforeseen issues, the region can expect to see the bridge structure taking shape above the Newry River by 2026, leading to the long-awaited opening roughly four years from commencement.

Funding and Budget

The Narrow Water Bridge is financed primarily through the Irish Government’s Shared Island Fund, with an allocation of €102 million (plus VAT) earmarked for the project. This funding commitment, equivalent to about €125 million including VAT, covers the full construction contract and related costs. Notably, the entirety of the bridge’s capital cost is being borne by Dublin – a reflection of the Irish government’s policy of investing in North-South connections under the Shared Island initiative. (The New Decade, New Approach agreement of 2020 had reaffirmed the bridge as a priority cross-border project.) Initially, earlier iterations of the project had lower cost estimates and even an offer of EU funding (~€17 million) back in the 2010s, but those funds were withdrawn when the project stalled. In the current revival, Ireland’s government ensured full funding so the build could proceed “without undue delay.” The official budget of €102m (approx. £87m) was confirmed when the construction contract was awarded in 2024. As of May 2025, officials insist the project remains within budget – Tánaiste Micheál Martin stated that he believes it can be delivered for the allocated amount, noting that rigorous project controls are in place via Louth County Council. There is no toll planned for the bridge, and ongoing maintenance funding will likely be a cooperative effort, though these details will be agreed closer to opening. For now, the Shared Island Fund’s commitment covers all major expenses, and no additional budget overruns have been reported. This unprecedented investment in a relatively small region underscores the project’s symbolic importance to cross-border unity.

Government and Political Updates

Political support for the Narrow Water Bridge has been strong and bipartisan in both jurisdictions since 2024. The Irish government’s top officials have been closely involved – at the June 2024 groundbreaking, then-Taoiseach (acting) Simon Harris hailed the bridge as “a game-changer for commerce, daily life and tourism in this part of our shared island”, crediting decades of community campaigning for making it possible. Tánaiste Micheál Martin, who as Taoiseach launched the Shared Island Unit, likewise called the project a “defining, iconic symbol” of North-South reconciliation and cooperation. On the Northern Ireland side, ministers were present despite the Stormont government’s suspension – the (former) Infrastructure Minister John O’Dowd attended the June 2024 launch and welcomed the Irish investment, calling the day “historic and significant” for the area. In subsequent months, leaders continued to highlight progress. At a North South Ministerial Council meeting in late 2024, First Minister-designate Michelle O’Neill noted all ministers were pleased with the bridge’s progress and reiterated the late 2027 completion expectation. Local representatives have also been active: Chris Hazzard, the MP for South Down, in May 2024 urged Newry, Mourne and Down Council and Louth County Council to coordinate supporting projects to maximize the bridge’s impact. He emphasized that Narrow Water Bridge will be “much more than an infrastructure project” and called for improved feeder roads, greenways, and tourism amenities to complement it. Politically, the project enjoys rare universal approval – politicians from all major parties (north and south) have spoken in favor, seeing it as a tangible benefit of peace and partnership. The UK Government has not needed to fund the bridge, but it has raised no objections; and the project was explicitly referenced in the 2020 UK-Ireland New Decade, New Approach deal. Overall, since 2024 political involvement has focused on monitoring delivery and celebrating milestones, with frequent statements of support but no significant controversies. In short, the Narrow Water Bridge has become a flagship example of cross-government cooperation on the island of Ireland.

Environmental Impact and Mitigation

Given the sensitive Carlingford Lough habitat and the nearby heritage sites, the Narrow Water Bridge project has been subject to rigorous environmental assessments. Both Ireland and Northern Ireland’s planning authorities approved the project with strict conditions to mitigate ecological impacts. In-water works are heavily timed to avoid wildlife disruption – for example, the project’s construction license prohibits any pile-driving during critical periods for aquatic and avian life (no piling from March through June, and none from September through February). This effectively limits pile installation to the summer months, reducing harm to migrating salmon (spring smolt run and autumn upstream migration) and protecting any nearby nesting birds during spring. When piling is underway, contractors must monitor vibration levels to ensure the noise/disturbance stays within tolerances, and heritage experts from the Historic Monuments unit monitor impacts on the 16th-century Narrow Water Castle across the river. The project also implemented a robust Construction Environmental Management Plan: runoff and stormwater from the site must be captured and treated (no direct discharge to the lough), and turbidity in the water is monitored so that sediment stirred up by works doesn’t smother marine life. To protect bats that forage along the river, the bridge design avoids any lighting under the deck and uses only upward-facing cable lights at night so as not to create light pollution along the waterway. The opening span’s operation was scrutinized in a Habitat Regulations Assessment to ensure that periodic openings for boat traffic won’t significantly alter water flow or wildlife patterns. On land, construction fencing and noise controls are in place near sensitive areas, and an archaeologist is on call during earthworks in case any historical artifacts are uncovered. Both Louth County Council and NI’s Department of Agriculture, Environment and Rural Affairs (DAERA) ran public consultations on the environmental reports – for instance, DAERA held a Marine Licence consultation in early 2024 for local input on the bridge’s marine construction aspects. In summary, the project is proceeding with a careful eye on the environment: with seasonal work windows, continuous ecological monitoring, and cross-agency oversight to ensure Carlingford Lough’s natural and historical heritage is safeguarded even as the bridge rises.

Community Engagement and Public Opinion

The Narrow Water Bridge has deep roots in the local community – the project was first proposed decades ago and championed by residents, local councils, and business groups on both sides of the border. Now that construction is underway, community engagement remains positive and proactive. Local public opinion is overwhelmingly supportive of the bridge, seeing it as a long-awaited connection that will benefit tourism, shorten travel times, and symbolically unite the region. For years, a cross-community advocacy group – the Narrow Water Bridge Community Network (NWBCN) – lobbied for the project, organised local meetings, and kept the public informed through newsletters and social media. That network continues to share updates and historical context, celebrating each milestone. Public information sessions were part of the planning process (as evidenced by the consultation on the marine licence in 2024), and local stakeholders had opportunities to voice concerns or suggestions, many of which were integrated into the project’s environmental and traffic management plans. Now during construction, the contractors and councils have maintained outreach to keep residents aware of upcoming works (e.g. temporary road arrangements or noise-intensive activities). Local businesses have expressed excitement at the prospects the bridge brings – for example, hotel and restaurant owners in Warrenpoint and Omeath have described the bridge as a “second chance” for the area to flourish as a tourist destination. The bridge will link communities that are only a few hundred meters apart but historically felt distant due to the lack of a crossing. In recognition of this, community leaders like MP Chris Hazzard emphasize the need to integrate the project with local amenities: improved walking/cycling routes connecting Omeath, Carlingford, Warrenpoint, and Rostrevor are being planned so that the bridge immediately slots into a network of trails and attractions. The two county councils (Louth and Newry, Mourne & Down) have been coordinating on these complementary projects, often with community input. Public consultation events have also focused on aesthetic and cultural elements – for instance, discussions on signage, interpretive panels about the area’s history, and ensuring the design of the bridge’s approaches is in harmony with the scenic landscape. Community sentiment in 2025 is largely proud and optimistic: the bridge is seen as “our bridge”, a symbol of how far the region has come. Even as heavy machinery works on site, local residents frequently stop at viewpoints to watch the progress. The general manager of a Warrenpoint hotel captured the mood, telling BBC News that the construction is “great news for the local economy” and that both towns are looking forward to the footfall and investment the open bridge will bring. In essence, the Narrow Water Bridge enjoys a rare status as a publicly championed infrastructure project – shaped by community advocacy and warmly anticipated by the people it will connect.

Visual Updates and Drone Footage

Drone photograph (March 2025) of the Narrow Water Bridge construction site, looking down the Newry River. Steel piles have been driven into the riverbed for the bridge’s piers/abutments, and a barge and crane are in place on the Co. Louth side (left bank).
One striking aspect of the Narrow Water Bridge build has been the regular visual documentation shared with the public. Local aerial photographers and enthusiasts have been providing frequent drone footage updates, giving the community (and viewers online) a bird’s-eye view of construction progress. High-resolution drone videos, often posted monthly, show key developments – from the clearing of Hall’s Wood on the northern approach, to the installation of a temporary work platform on the lough, and the drilling of piles into the water. By March 2025, for example, drone images revealed rows of rust-colored foundation piles protruding from the river on the Omeath side, outlining where the bascule span’s pivot will rest. Heavy equipment like the “Coastbuster” workboat and floating barges can be seen in the footage, delivering materials and serving as a base for piling in the tidal waters. These aerial views (often shared by local drone pilot Gerald McGivern of Seehigher) have become a popular attraction on social media – some update videos have tens of thousands of views, underscoring widespread interest. The project’s contractors themselves have embraced this transparency: in one case the marine contractor Coastworks shared spectacular drone photos of their barge in action, crediting the photographer and highlighting the collaborative pride in the project. The imagery not only satisfies curiosity but also builds support by showing that “work is happening on the ground” in a tangible way. Viewers can observe the concrete foundations of the south pylon taking shape, the outline of the abutments on both shores, and the assembly of a crane that will eventually lift steel bridge segments into place. As the bridge rises, officials plan to continue this visual engagement: periodic drone flyovers and perhaps time-lapse cameras will chronicle the cable-stayed span and the lifting span being installed. For a project so long in the imagination, these real-time images and videos have been inspiring – turning what was once an artist’s render into an evolving reality before the public’s eyes. By the time of opening, the Narrow Water Bridge will have been one of the most visually documented infrastructure projects in Ireland, reflecting a new era of community-engaged development.

Sources: Official Department of Taoiseach and NI Department for Infrastructure press releases; Roughan & O’Donovan engineering updates; local news coverage by Newry Reporter, Irish News, BBC NI; statements by government officials in 2024–25; planning and environmental documents (DAERA Marine Licence); and ongoing progress reports from community groups and drone photographers, especially the stunning work of Gerard McGivern.