05 Sep 2026

Click on images for CPD Dashboard

Britain and Ireland’s Infrastructure Problem Is No Longer Hidden

The September 2026 update to the CPD infrastructure dashboards gives the public a clearer view of a problem that is usually buried in separate press releases, committee papers and project webpages.

Across 240 major schemes in Northern Ireland, the Republic of Ireland, Scotland, Wales, London and England, the pattern is now hard to miss. Projects are announced with confidence, delayed with routine language, reset through procurement, and then re-costed years later as if the delay itself had no price.

It does have a price. The CPD dashboards show it ticking up in real time.

The headline

The latest September refresh found 29 material project updates across the 240-scheme tracker. These were not minor traffic notices or routine political comments. They were changes to cost, delivery stage, planning, procurement, funding, programme risk or governance.

The broad verdict is simple: the public infrastructure system is still better at announcing projects than delivering them.

Some schemes are moving. Some are opening. Some have reached useful construction or planning milestones. But the overall picture is still one of delay, cost exposure and repeated reset.

Scotland: movement, but still too much rescue work

Scotland saw some of the most important September changes.

The Scottish Programme for Government 2026-2031 included a commitment to conclude a new A9 framework agreement for remaining sections and to award the Pitlochry to Killiecrankie contract (Scottish Government). It also set out wider capital-delivery changes, including a Scottish Government bond programme and a new Major Projects Office (Scottish Government).

That sounds positive, and parts of it are. But the need for new frameworks, new offices and new funding routes also tells its own story. Major infrastructure is still having to be rescued, reorganised and re-explained long after the public first heard the original promises.

The ferry story reinforces that point. Around £20 million of additional funding was reported for island ferry vessels, adding another warning mark to Scotland’s already troubled ferry-delivery record (UK Defence Journal). The public do not just see a bigger number. They see a system where the final cost keeps arriving after the original case has already been sold.

Ireland: building, but at a price

The Republic of Ireland continues to show the uncomfortable split that the CPD dashboard was built to expose. The South is often better than the North at getting schemes moving, but it pays heavily for that delivery.

Cork Area Commuter Rail recorded an important step forward, with planning permission reported for the Kilbarry/Blackpool station and construction expected from 2027, while Dunkettle remained pending (Irish Examiner). That is genuine progress.

Dublin Airport’s passenger-cap issue also moved forward legally, but the risk has not disappeared. The new statutory route still leaves planning assessment, consultation and European legal uncertainty in the frame (RTÉ).

In plain English: Ireland is still building, but it is too often building after the budget has already lost credibility.

Northern Ireland: the cost of not delivering

Northern Ireland’s September update is quieter, but no less important.

There was additional support for the North West Short Courses Programme linked to Magee expansion, and updated NI Water price-control information from the Utility Regulator (Department for the Economy NI, Utility Regulator NI). There was also a consultation on future water and sewerage guidance for 2028/29 to 2032/33 (Department for Infrastructure NI).

But the bigger issue remains unchanged. Northern Ireland has too many schemes that appear regularly in public discussion without moving decisively into delivery.

That matters because low spending is not the same as good cost control. A region cannot claim success simply because projects remain stuck. If a road, stadium, interchange, campus or water scheme is announced, debated, redesigned and delayed for years, the public still pays. It pays through inflation, through lost economic benefit, through professional fees, through repeated process, and through reduced confidence.

This is why the dashboard now treats poor delivery more sharply. A system should not be rewarded for paralysis.

Wales: not perfect, but currently strongest

Wales remains the strongest overall performer in the British Isles dashboard.

That does not mean Wales has no problems. It has major projects, funding pressure and long-term delivery risk. But compared with the other jurisdictions, it currently shows the best balance between cost control and delivery.

The September update added Welsh Government progress on NHS capital support, Transport for Wales ticketing expansion and bus-fare support, while Tata Steel confirmed the Port Talbot electric arc furnace commissioning window as late 2027 to early 2028 (Welsh Government, Tata Steel UK).

The lesson is not that Wales is a model of perfection. It is that relative performance matters. When every jurisdiction has problems, the question becomes: who is managing the balance least badly?

At present, the dashboard says Wales is ahead.

London: progress with giant liabilities attached

London’s position is different again. It can deliver at scale, but its risks are enormous.

Old Oak Common recorded a visible construction milestone, with the first six HS2 platforms completed in the underground station box (LBC). That is progress the public can understand.

But Heathrow expansion shows the other side of London infrastructure. The Mayor of London and TfL opposed the expansion national policy statement, with surface-access costs reported as a potential unfunded liability of up to £9 billion (BBC News).

That is the London problem in one sentence: big projects, big milestones, and very big unresolved bills.

England: the reset culture continues

England remains dominated by schemes where the numbers and delivery dates have shifted dramatically from the original public promise.

In September, Sizewell C saw a contractor substitution on a highways package, Bristol Temple Meads recorded an opening milestone for its eastern entrance, HS2 appointed a new Chief Programme Officer, and the Teddington Direct River Abstraction procurement strategy was reset (Highways Magazine, Network Rail, Rail Business Daily, Construction Enquirer).

Each item has its own explanation. Taken together, they show a familiar pattern: procurement changes, governance changes, delayed certainty and rising exposure.

That is why the dashboard is useful. It does not let each reset disappear into the next headline.

Why the live cost clock matters

The live cost clock is deliberately blunt.

It says that delay is not neutral. Every second a major unresolved scheme remains undelivered, the original estimate is exposed to inflation, market change and risk.

The clock is not pretending to be a final account. It is a warning light. A high cost-per-second figure tells the public that an undelivered portfolio is still absorbing value even when nothing visible is happening on site.

Lower cost per second generally suggests a more contained exposure, a better initial estimate, or a smaller unresolved portfolio. Higher cost per second suggests the opposite. It is not the whole story, but it is a useful way of making delay visible.

And visibility matters. Without it, slow failure looks like normal administration.

The key point: do not reward paralysis

One of the most important changes in the dashboard is the clearer separation between cost performance and delivery performance.

This matters most when comparing Wales and Northern Ireland. If a combined score makes them look too close, the weighting needs to be challenged. Wales has problems, but it is performing better overall. Northern Ireland’s delivery record is weaker, and that weakness should be shown plainly.

The dashboard must not reward a place for spending less if the reason is that it has failed to build. A scheme that sits for years in planning, consultation, funding dispute or political limbo is not a saving. It is a deferred failure.

That is the point taxpayers understand instinctively. They do not only ask whether the final bill went up. They ask why the thing was not built when they were told it would be.


The September verdict

The September 2026 CPD update does not say every project is failing. It says something more serious: the failures are systematic enough to measure.

Across the dashboard, the same themes keep appearing. Early announcements. Weak original estimates. Planning risk. Procurement resets. New funding gaps. Delayed starts. Revised completion windows. Extra governance. More reports. More explanations.

The public has heard plenty of announcements. What it needs now is delivery.

That is why CPD matters. It gathers the scattered public record and puts it in one place. It lets anyone ask the basic questions that should have been asked from the start:

  • What was promised?
  • What was the original cost?
  • When was it meant to be finished?
  • What does it cost now?
  • When will it actually be delivered?

In September 2026, the answer across Britain and Ireland is uncomfortable. Too many projects are still being announced faster than they are being built.